Details

Following Storm Doris in February 2017, we were commissioned to carry out repairs at Valley Road Industrial Estate, Birkenhead. Many roof panels had come loose exposing the building and creating a hazardous environment. High Access arrived on the scene within 2 hours of the initial call and safely removed and secured all loose roof panelling.

Works carried out:

  • Cut down all loose and dangerous external roof sheets
  • Cutting in controlled sections to manage weight of roof sheets
  • Stored all waste at ground level
  • Removed all loose debris from roof and site
  • Secured remaining roof liner panels
  • Supply and installation of seven liner sheets at 3.7m
  • Safe navigation of the roof via easi-dec roofing systems.

Equipment deployed:

  • Four working at height maintenance operatives
  • SSSTS site supervisor
  • 46m truck mounted access platform with IPAF operatives
  • 10m Internal scissor lift with IPAF operatives